Complex Load Shape Lift

Project Summary

Client: Civ2Con

Location: 682 Dohertys Rd Truganina

Crane: LTM1200 + AT20

Project Overview

Complex Load Shape Lift

CHALLENGE: Due to the complex geometric shape of the load, a range of different rigging equipment was required to transport, handle and install the load. Moreover, the adjacent powerlines to the trench added a level of difficulty to the lift plan and execution.

SOLUTION: Premier Cranes strategically planned a slew path that avoided all power lines. In addition a Franna was used to rotate the load, whilst a chain block supported the tilting angle of the load during installation.