Project Summary
Client: Murra Warra Wind Farm
Location: Murra Warra
Crane: 500T Liebherr + 200T Liebherr
Project Overview
CHALLENGE: This wind farm project required us to work with McNally’s 500T crane using rotating column bases for installation. This project presented a number of challenges. It required us to use precise sequencing to lift 40-50 tonnes in extremely windy conditions, in coordination with another crane company.
OUTCOMES: To ensure that the job was done safely and efficiently, we undertook a series of lift studies during the planning stages in order to formulate and document the necessary sequence. On the ground, our skilled team coordinated with our partners to carry out this sequence with precision despite the adverse wind.