Road and Bridge Upgrade

Project Summary

Client: Civ2Con

Location: Truganina, Victoria

Crane: Liebherr LTM 1200

Project Overview

Road and Bridge Upgrade

CHALLENGES: To plan and execute the lift of precast culverts, each weighing 9t, into place alongside a live roadway and close to powerlines. The site setup along with requirements from VicRoads added extra challenges for the planning and operations teams.

OUTCOMES: The planning team used a combination of site visits and design software to create a plan that utilised the Liebherr LTM 1200 and our experienced team of precast concrete panel riggers in two locations on either side of the road. Our compliance team worked with VicRoads to meet all their document and SWMS requirements. The operations team executed the plan to meet the challenges of the project with our #TeamLifting can-do attitude Premier Cranes has become famous for. We look forward to working with Civ2Con again in the future.