Precision at 40m: Train Bogie Lift with the LTM1250
Project Summary
Client: Gemco
Location: 7 Westlink Court, Altona
Crane: Liebherr LTM 1250-5.1
Project Overview
Premier Cranes & Rigging was engaged by Gemco to lift three 12-tonne train bogies into a storage area in Altona.
The lift used our 250t Liebherr LTM 1250-5.1,with the lift plan showing the crane working at approximately a 40m radius with a 47.6m main boom and 88t of counterweight.
While the individual bogies were 12t, the planned lifted load including the hook and other allowance was approximately 13.04t, placing the crane at 93.8% of the planned maximum capacity at the critical position.
Challenge
Long Radius, High Utilisation
The main challenge was not simply the weight of the bogies, but where that weight needed to be placed.
At the approximately 40m working radius shown in the lift study, the selected crane configuration provided 13.9t capacity, making accurate crane positioning and adherence to the engineered lift plan critical.
The Solutions
Plan the Setup Around the Critical Lift
The LTM 1250-5.1was configured with 47.6m of main boom, 88t counterweight and a 9.30m × 8.30m outrigger footprint, giving the crew the required configuration for the planned lift.
Before lifting, the SWMS required the crew to assess the setup area and ground conditions, confirm underground services, review ground bearing pressure requirements and position bog mats and outriggers in accordance with the lift plan.
The load itself also had to be checked for weight, dimensions, centre of gravity and lifting points, with the rigging selected and inspected before work commenced.
Controlled Execution
With three bogies to move into the storage area, each lift required the same controlled process rather than treating it as a routine pick.
The SWMS called for a test lift of approximately one metre to confirm the rigging was correctly seated and the load secure.
Exclusion zones, communication between the operator and dogger/rigger, and load control remained in place throughout the operation.
THE OUTCOME
A 12t load does not automatically mean a small lift - radius, crane configuration, ground conditions and final placement determine the real lifting challenge.
This job is a good example of why the lift plan matters before the hook ever takes the weight.