Gatic Lids Installation at New Footscray Hospital

Gatic Lids Installation

Project Summary

Client: Multiplex

Location: New Footscray Hospital

Crane: LTC 1050-3.1

Project Overview

Gatic Lids Installation

Premier Cranes & Rigging was engaged by Multiplex to execute the installation of Gatic lids as part of the New Footscray Hospital project. This critical infrastructure development required the utmost precision and efficiency, particularly given the challenging site conditions, which included low headroom and restricted slewing space. The team was tasked with delivering a solution that not only met these challenges but also adhered to the stringent safety and quality standards required by the project.

CHALLENGE:
The installation site posed several significant challenges:
1. Low Headroom: With only 1.8 metres of headroom available, conventional lifting methods were not feasible, necessitating a tailored approach.
2. Multiple Lifting Points: To ensure safety, as advised by the manufacturer, the lids required multiple lifting points, adding complexity to the rigging setup.
3. Limited Slewing: The tight space restricted the slewing capability, demanding precise manoeuvring and control.

SOLUTION:
To overcome these obstacles, Premier Cranes & Rigging used the LTC 1050-3.1 crane, equipped with a THKH fly, an offset fly, and an engineered rigging solution:

1. LTC 1050 Crane with THKH Fly: This crane, equipped with an offset fly and an engineered rigging solution, was selected for its ability to operate efficiently within the restricted headroom.
2. Centre Lifting Beam: A custom-engineered centre lifting beam was used to distribute the load evenly across the multiple lifting points, ensuring safety and stability.
3. Customised Solutions for Diverse Lids: The project involved five different types of lids, each requiring a unique lifting solution. Our engineering team developed and implemented five different rigging solutions to comply with the manufacturer's standards while accommodating the low headroom.
4. Coordination was key in this project: We worked closely with the trades, builders, and structural engineers through multiple high-risk workshops, ensuring that every aspect of the installation was thoroughly planned and executed.

The Liebherr LTC 1050-3.1 crane truly showcased its capabilities during this project. Its ability to operate in a confined space with precision allowed us to complete the installation without compromising on safety or efficiency. The crane’s narrow design and powerful lifting capacity made it possible to navigate the low headroom environment, while its advanced control systems ensured smooth operation despite the restricted slewing capability. This project highlighted the versatility and reliability of the LTC 1050-3.1, making it an invaluable asset in complex lifting scenarios.

CONCLUSION
The project was completed successfully with the installation of 25 pits in just two days, showcasing Premier Cranes & Rigging’s ability to deliver complex lifting projects safely and efficiently, even under challenging conditions. This achievement was a true collaborative effort between the installer, structural engineer, Premier, and the builder, who worked together to overcome various challenges. Our innovative approach and commitment to collaboration ensured that the installation met all safety standards and was completed within the tight project timeline.




Video Example